BRDC has sought and found a site large enough to make a significant contribution to the local housing stock that is affordable and available to the local workforce. After due diligence, BRDC purchased a 30-acre site on Butler Road in Boothbay in 2023.
By targeting a large parcel with the potential for a significant number of housing units and raising private funds to help finance the acquisition and extension of necessary utilities, the project will be able to leverage that investment to help finance the future phases with state and federal funding programs, supplemented by modest sales proceeds.
The concept plan for this site takes a phased approach to development of the parcel and was informed by a design development team selected by BRDC. The first phase included land acquisition and extension of water and sewer to the site. The second phase, in production now, is an affordable home ownership project targeted to our workforce. It will create 20 for-sale condominium townhomes with prices affordable to those making no more than 120% of Area Median Income.
Future phases could include apartments, single-family homes, and a additional townhouse condominiums. Below is an example of what full buildout might look like. The goal is to create a range of housing choice, both for-sale and for-rent, that is affordable to Boothbay’s workforce at a range of income levels.
Progress to-date:
6/2022 -Formation of BRDC
7/2022 -Public Meeting With Boothbay Selectboard: Received Unanimous Letter of Support
9/2022 -Phase I Environmental Site Assessment: No Concerns Found
9/2022 -Public Meeting With Boothbay Harbor Selectboard: Received Unanimous Letter of Support
9/2022 -Public Meeting With Boothbay Water District: Advancing Infrastructure Design
10/2022 -Public Meeting With Southport Selectboard: Received Unanimous Letter of Support
10/2022 -Public Meeting With Edgecomb Selectboard: Received Unanimous Support
10/2022 -Public Meeting With Boothbay Harbor Sewer District: Advancing Infrastructure Design
11/22 -Survey and Wetland Delineation Complete: Advancing Site Planning Design
11/2022 -Infrastructure Survey and Geotechnical Investigation Complete: Advancing Infrastructure Design
11/2022 -Geotechnical Investigation Complete for Property: Advancing Infrastructure Design
12/2022 -Phase II Environmental Site Assessment: No Concerns Found
2/2023 -TIF Presentation to Town of Boothbay Selectboard: Approval for Public Vote Received
2/2023 -Receive 501(c)(3) Non-Profit Status: Effective Date of June 3, 2022
4/2023 -Wetland Classification Complete: No Vernal Pools Found
5/2023 -Town meeting voters approval of $50,000 in Boothbay ARPA Funds for Infrastructure Construction
5/2023 -Town meeting voters approval of $1,500,000 Boothbay TIF Expansion for Infrastructure Construction
6/2023 -Purchase of Butler Road Property
7/2023 -Meeting Held with CEI to Secure Home Ownership Counseling Partner
7/2023 -Meeting Held with Genesis Community Loan Fund to Secure Bridge Lender
7/2023 -Meeting Held with Bangor Savings Bank to Secure Lender/Financing
10/2023 -Awarded $300,000 ARPA Grant from Lincoln County
11/2023 -Town of Boothbay signs Construction contract for water and sewer extension
3/2024 -Retaining wall and culvert complete
6/2024 -Site connected to public water & sewer
8/2024 -Access road to Butler Road site complete
8/2024 -Site prepared for installation of pumping station